Why most Salesforce projects get their UAT phase wrong

Pierre FrinJune 20267 min read
Dev UAT ⚠ Too short Production Bug in prod SALESFORCE · UAT · QUALITY

I have worked on dozens of Salesforce projects. And I have seen the same pattern repeat every time a go-live turns into a disaster: the UAT phase was badly designed, rushed, or both.

This is not a technical problem. It is a problem of organisation and planning. And it is always created long before UAT begins.

The 5 mistakes that wreck Salesforce UAT

1. UAT is scheduled too late and made too short

The classic pattern: development runs late, the overall schedule does not move, and the UAT phase is squeezed to hold the go-live date. Three planned weeks become five actual days.

The result: testers do not have the time to cover every scenario. Non-critical defects are parked “in the backlog” and end up in production. Quality debt starts building on day one.

UAT does not compress. If development runs late, it is the go-live that has to move, not UAT that has to be crushed.

2. The wrong people run the tests

This is the most common mistake. UAT is handed to the developers, to the IT team, or to a project manager who knows the system better than any user does. Those people test what they designed, with clean data and predictable scenarios.

What you need instead: end users. The sales reps who will log an opportunity straight after a phone call. The customer service team handling a complex case with real data. They are the ones who find the real problems.

3. There are no defined acceptance criteria

Is a defect a blocker or not? Asked during UAT with no pre-agreed answer, that question creates endless arguments between the project team and the customer. Everyone has their own definition of “acceptable”.

The fix: define the acceptance criteria before development starts, not during UAT. What blocks the go-live? What can wait for the first patch? That framing has to exist in writing.

4. The test data looks nothing like production

UAT runs on 10 clean accounts, with well-filled fields and linear scenarios. Production is 50,000 accounts with missing data, special characters in names, and edge cases nobody had anticipated.

Testing with data that looks nothing like reality buys peace of mind without reducing the real risk.

Ideal: use an anonymised data set extracted from production (or from the source system). If that is not possible, build edge cases by hand: empty fields, extreme values, duplicate records.

5. There is no UAT lead

UAT is organised, the testers are named, defects are logged in a spreadsheet. But nobody owns tracking progress, prioritising fixes, or deciding what is a blocker and what is not.

Without a clearly named lead, UAT drifts. Defects pile up without being dealt with. Decisions are not made. And the go-live gets closer.

How to run a Salesforce UAT that works

01
Define the acceptance criteria before development
Blocker, non-blocker, cosmetic: every category has a written definition approved by the customer and the project team.
02
Involve end users from the moment the scenarios are designed
They are the ones who know the real edge cases. Having them help write the test scripts is as valuable as having them in the UAT room.
03
Prepare a representative data set
Missing data, extreme values, duplicate records: the problems that exist in production have to exist in UAT.
04
Appoint a UAT lead with decision-making authority
One person who can prioritise fixes, rule on whether a defect is a blocker, and make the go-live call.
05
Protect the time allowed for UAT
If development runs late, the go-live moves, not UAT. That rule is not negotiable.

The sign that UAT is going to go well

Projects whose UAT goes well all have one thing in common: end users were involved early. Not just at UAT, but from the design workshops onwards. They helped define the scenarios, they signed off the mockups, and when UAT starts they know what they are going to test and why.

UAT is not a stage at the end of a project. It is the outcome of a validation process that starts at the very first workshop.

Pierre Frin
CRM consultant · Adobe Campaign · Salesforce · Imagino · Grokium

A Salesforce project to de-risk?

The scoping call is free and with no commitment. 30 minutes to define the scope and confirm feasibility.

Contact →
Go further
My CRM services All technical articles Contact me